Building a Flood Defense System in Can Tho City, Vietnam
Home to 4.2 million people, Can Tho City is a major urban center in Viet Nam and plays an important role as a transport, commercial and industrial hub for the Mekong Delta. Chronic seasonal flooding, however, causes significant economic losses to the city and hampers its ability to fulfill its potential. Floods cost the city an estimated $300 million a year. This could now rise as the Mekong Delta is acutely vulnerable to climate change, ranking among the top four areas in the world most threatened by sea-level rise.
The Can Tho Urban Development and Resilience Project has been front and center in the government of Vietnam’s response. Backed by a $250 million loan from the World Bank and implemented between 2016 and 2024, the project constructed a flood-defense system along the Can Tho and Khai Luong rivers to shield Can Tho City’s urban core, an area covering some 2,700 hectares. GFDRR-funded analysis which provided Can Tho City a strategic flood risk master plan informed the design of the project with, for instance, its focus on the Can Tho urban core directly stemming from that analysis.
Under the flood defense system supported by the project, key components—tidal sluice gates, ship locks, upgraded canals, and improved river embankments—were combined with elevated roads to form a protective “ring embankment.” This system was put to the test in October 2023. When the Can Tho River swelled, residents braced for the familiar inundation. However, the water stayed out as tidal sluice gates in city’s new drainage and defense system held back the encroaching river.
The project treated flooding not just as an engineering challenge but as part of a broader urban development strategy. Accordingly, planners recognized that easing pressure on the flood-prone urban core required better connecting it to safer, higher ground, particularly to the south. Consequently, the project also funded the construction of two major bridges, the Quang Trung and Tran Hoang Na bridges, aiming to make southern areas more attractive for settlement and development.
The impact is already palpable, according to Vo Hoang Nga, a community leader in the Xuan Khanh Ward in the city’s Ninh Kieu District. “It’s now easier for people on both sides to get around and do business,” he said. “It used to take at least an hour to cross the river, and accidents happened all the time.” He noted that residential areas across the river, which were once difficult to access, are now developing and attracting more residents.
Beyond preventing flood damage, the project helped bolster economic stability for businesses and reduce public health risks associated with contaminated floodwaters. And some new infrastructure serves dual purposes: Embankments double as parks and pedestrian walkways, enhancing the urban landscape.
Officials report that chronic flooding has been reduced significantly in the core urban area, where seasonal high water once inundated up to half the built-up zones. More than 420,000 residents in the protected areas remained dry during recent rainy seasons.
“Residents of Can Tho City strongly support the project and are delighted with the results,” said Nguyen Thuc Hien, former vice chair of the municipal People’s Committee.
Beyond concrete and steel, the project broke new ground in Viet Nam by integrating physical defenses with sophisticated digital systems, supported by a $10 million grant from the Swiss State Secretariat for Economic Affairs. A new Flood Risk Management Information System (FRMIS) deploys 60 sensors at flooding hotspots, creating real-time monitoring capabilities that feed into a central command center with remote flood control capabilities. The system also runs simulations using historical data and weather forecasts, enabling authorities to anticipate flooding events.
Complementing the FRMIS is a new Spatial Planning Platform, which integrates data from various municipal departments. This platform provides a comprehensive overview for decision making related to urban planning, disaster risk management, and public service provision. Its Integrated Social Assistance system is designed to quickly activate support for vulnerable residents during disaster events.